(Summary description)At 8:18 am on February 18, the first steel column of Yinzhou Butterfly Lake Project began to be hoisted, marking the official start of the steel structure project. The project is located in Huilong Town, Qidong City, Nantong City, Jiangsu Province. It is the future core area built by the government - Diehu Plate, with a total area of 81,900 square meters and a planned total construction area of about 376,000 square meters, of which the above-ground construction area is 235,000 square meters. meters, with an underground construction area of 141,000 square meters. The Butterfly Lake Project consists of two 239-meter super high-rise towers, east and west podiums and two-storey basements, of which the east tower has 44 floors, the podium has 4 floors, the west tower has 43 floors and the podium has 3 floors. The steel consumption exceeds 10,000 tons. Highly refresh the city skyline and become the latest landmark of Qidong's rise. The main steel structure of the project is a rigid column, which intersects with the whole civil construction. The column-beam joints are particularly complex, and most of them use steel bar connectors, which have extremely high requirements for the installation of the steel structure. The main beam of the banquet hall in the podium is 35.5 meters long and cannot be hoisted by conventional mechanical equipment. In order to facilitate the smooth progress of the construction, a tripod bracket after review and calculation is used. . Each of the twin towers has a double-curved tower crown, which adopts a continuous surface design. The elevation of the bottom of the tower crown is about 199 meters, and it gradually shrinks from large to the crown top. The whole is completed in one go, emphasizing the identity of the tower crown and the overall project. The project department will take the successful completion of the first hoisting as an opportunity to continue to keep the epidemic prevention and control unsettled, and ensure the safety of production, optimize on-site control measures according to local conditions, complete the project delivery with high quality and quantity, and build a landmark building in Qidong New City, in order to realize the national high-quality project. A solid foundation has been laid for the excellence goal of the Gold Award!
- Categories:Company News
- Author:
- Origin:
- Time of issue:2022-02-21 15:05
- Views:
At 8:18 am on February 18, the first steel column of Yinzhou Butterfly Lake Project began to be hoisted, marking the official start of the steel structure project.
The project is located in Huilong Town, Qidong City, Nantong City, Jiangsu Province. It is the future core area built by the government - Diehu Plate, with a total area of 81,900 square meters and a planned total construction area of about 376,000 square meters, of which the above-ground construction area is 235,000 square meters. meters, with an underground construction area of 141,000 square meters.
The Butterfly Lake Project consists of two 239-meter super high-rise towers, east and west podiums and two-storey basements, of which the east tower has 44 floors, the podium has 4 floors, the west tower has 43 floors and the podium has 3 floors. The steel consumption exceeds 10,000 tons. Highly refresh the city skyline and become the latest landmark of Qidong's rise.
The main steel structure of the project is a rigid column, which intersects with the whole civil construction. The column-beam joints are particularly complex, and most of them use steel bar connectors, which have extremely high requirements for the installation of the steel structure.
The main beam of the banquet hall in the podium is 35.5 meters long and cannot be hoisted by conventional mechanical equipment. In order to facilitate the smooth progress of the construction, a tripod bracket after review and calculation is used. .
Each of the twin towers has a double-curved tower crown, which adopts a continuous surface design. The elevation of the bottom of the tower crown is about 199 meters, and it gradually shrinks from large to the crown top. The whole is completed in one go, emphasizing the identity of the tower crown and the overall project.
The project department will take the successful completion of the first hoisting as an opportunity to continue to keep the epidemic prevention and control unsettled, and ensure the safety of production, optimize on-site control measures according to local conditions, complete the project delivery with high quality and quantity, and build a landmark building in Qidong New City, in order to realize the national high-quality project. A solid foundation has been laid for the excellence goal of the Gold Award!
Contact Us
Address: #6, Qiannong 1st Road, Xiaoshan District, Hangzhou, Zhejiang, China
E-mail:dadi@cnzjdd.com
- Tel
-
E-mail
- E-maildadi@cnzjdd.com
- TOP
Copyright © Zhejiang Dadi Steel Structure Co., Ltd. All rights reserved. Powered by www.300.cn SEO