Full Steam Ahead! Several Key Projects at Dadi Steel Structure Reach New Construction Milestones


Secure Victory in the First Quarter, Strive for a Strong Start

Dadi Steel Structure Bolsters Its Spirited Efforts

Making Steady Progress Toward the Goal of High-Quality Contract Performance

Several key projects have successively reached critical milestones.

 

Block 013-02 of the Office Building Project for Neighborhoods 334 and 336 in Changhai Road Subdistrict

On March 30, the first steel structure lift for Plot 013-02 of the office building project in Blocks 334 and 336 of Changhai Road Subdistrict, which is being constructed by our company, was successfully completed.

Located in the Changhai Road Subdistrict of Yangpu District, Shanghai, the project has a total floor area of 61,521.7 square meters, with 47,070.7 square meters above ground and 14,451 square meters underground. The development comprises three 11-story high-rise headquarters office buildings, connected at their upper levels by skybridges. The project aims to foster a “science-and-tech innovation ecosystem” that balances rigidity and flexibility, while striving to establish a model urban renewal district characterized by cultural heritage and a sustainable digital-industry headquarters community.

 

Shanghai Jinqiao South Zone WH7-3 JinGu General Industrial Building Project

On April 8, the topping-out ceremony for the main structure of the WH7-3 JinGu General Industrial Building project in the Southern Zone of Shanghai Jinqiao was successfully held.

 

The project is located in the Jinqiao South Industrial Zone of Tangzhen, Pudong New Area, Shanghai, with a total construction area of approximately 293,000 square meters. It comprises seven factory buildings and eight steel connecting bridges, with a total steel structure weight exceeding 30,000 metric tons.

In view of the project’s large scale, tight schedule, and the challenge of carrying out construction across the Spring Festival holiday, the project team undertook meticulous planning and close coordination among design, detailed drawing, fabrication, and installation processes. The construction scope was rationally divided into zones, and work was organized in a scientifically sound manner. On November 8, 2023, the first steel structure lift for the basement commenced; despite a suspension during the Spring Festival break, the structural topping-out of all factory buildings was successfully completed in just over four months. To further enhance project quality management, on January 13, 2024, the project office also hosted the company’s 2024 Shanghai Regional Stud Welding Skills Competition, which effectively accelerated and ensured the progress and quality of the floor decking and stud welding operations, thereby laying a solid foundation for the comprehensive advancement of the entire project.

 

Shanghai Jinqiao South Zone WH2-3 West Block JinGu General Factory Building Project

On April 8, the main structural topping-out of the JinGu General Industrial Building project in Block West of WH2-3, South Area of Shanghai Jinqiao, was successfully completed.

The project is located in the Jinqiao South Industrial Zone of Tangzhen, Pudong New Area, Shanghai, with a total construction area of approximately 136,000 square meters. It comprises seven factory buildings and eight steel connecting bridges, with the above-ground structures primarily featuring steel frame construction. The outdoor connecting corridors are supported by steel structural beams and columns, with a total steel consumption of about 19,000 metric tons. Upon completion, the project will become a new hub for the South Industrial Zone, further boosting the development of strategic emerging industries and productivity-enhancing service sectors.

 

General Contracting Project for the Testing Laboratory of Jinan Siemens Energy Transformers Co., Ltd.

On April 9, the first hoisting of steel columns for the laboratory building of Jinan Siemens Energy Transformer Co., Ltd.—a project under our company’s general contracting—was successfully completed. This marks another Siemens Energy project undertaken by our company, following our previous role as the general contractor for the Siemens Energy Testing Hall in Hangzhou.

Jinan Siemens Energy Transformer Co., Ltd. is Siemens Energy’s earliest manufacturing subsidiary in China and has been operating in the Chinese market for 30 years. The project is located at No. 10 Weihua West Road, Shizhong District, Jinan City. The facility measures 80.8 meters in length, 45 meters in width, and 44.15 meters in height, and comprises a high- and low-bay workshop.

 

The successful first lift for two new projects, coupled with the timely topping-out of the factory buildings on plots WH7-3 and WH2-3 in the South Area of Jinqiao, represent significant milestone achievements in project construction, laying a solid foundation for the orderly and comprehensive advancement of the project.

 

Office Building Project for Blocks 334 and 336 in Changhai Road Subdistrict, Plot 013-02; WH7-3 and WH2-3 in the Southern Zone of Shanghai Jinqiao; General Contracting Project for the Testing Laboratory of Jinan Siemens Energy Transformers Co., Ltd.